Case Study: Cleanroom Lighting & Systems Upgrade at North Middlesex University Hospital

Client: North Middlesex University Hospital NHS Trust Contractor: Hendry Construction Ltd

Project Overview

Hendry Construction was appointed to carry out essential upgrades within the specialist pharmacy cleanroom at North Middlesex University Hospital. The project included replacing cleanroom lighting, installing a modern intercom system, and modifying the door interlock infrastructure to ensure continued secure operation. All works were conducted in a live hospital environment, fully compliant with MHRA and ISO cleanroom standards, ensuring zero contamination risk and uninterrupted pharmaceutical output.

Objectives

  • Upgrade outdated fluorescent lighting to energy-efficient LED luminaires
  • Improve internal communication with a hands-free digital intercom system
  • Ensure compliant, secure door interlock and airlock operation
  • Minimise disruption and eliminate contamination risks

Scope of Works

Cleanroom Lighting Replacement

  • Removed legacy fluorescent fittings
  • Installed IP65-rated, sealed LED luminaires
  • Verified illumination to ISO Class 7 cleanroom standards
  • Lighting supplied by Solite, specialists in cleanroom lighting

Digital Intercom System Upgrade

  • Decommissioned existing analogue systems
  • Installed flush-mounted, hands-free digital intercoms
  • Integrated with existing pharmacy workflows

Door Interlock System Modifications

  • Rewired interlock system for correct sequencing
  • Maintained airlock integrity and pressure control
  • Tested and commissioned to ensure full compliance

Challenges & Solutions

  • Live Hospital Environment: Work was scheduled around pharmacy operations with phased planning
  • Cleanroom Protocols: All works conducted with HEPA-filtered workstations and full gowning procedures
  • Non-Standard Lighting Apertures: Custom-fabricated bezels provided seamless fitting for new luminaires

Project Outcome

  • ~30% reduction in energy use
  • Modern digital intercom system for seamless communication
  • Updated door interlock ensures secure and compliant access
  • Full MHRA and ISO cleanroom compliance
  • Zero disruption to pharmacy operations

Key Benefits

  • Improved energy efficiency and reduced maintenance
  • Enhanced communication and operational safety
  • Compliance with MHRA and ISO Class 7 cleanroom standards
  • Minimal disruption during installation
  • Specialist cleanroom lighting by Solite